From a pilot project to a successful solution
The leader of the Malaysian oil and gas industry launched a pilot project by installing the Multiphase Pump Technology at one of their fields.
The system was set up and successfully commissioned at Tembungo-B, an unmanned offshore satellite platform in Sabah Waters in August 2007.
The Tembungo oil fields consists on an integrated production and processing platform, the Tembungo-A and Tembungo-B. The unprocessed mixture of gas and crude from Tembungo-A is routed by a 6 inches trunk line departing to Tembungo-B.
In order to guarantee the customer the highest degree of security Bornemann installed an on skid control system.
Technical data:
| Size of equipment: | 1 MPC 208 |
| Uptime: | 99 % |
| GVF: | up to 100 % |
| Volume of mix: | 140 m³/h |
| ∆ pressure: | 21 bar |
| Installed power: | 240 kW |